R
Roland67
I have a schedule which contains numerous sub-project schedules. These
sub-projects have a considerable number of external links. I have been
making updates to the individual sub-projects. Recently upon opening a
sub-project I received a "circular relationship" error (the successors of a
task refer back to a predecessor of the same task). When I click on the OK
button Project comes up then goes what I can only guess as an infinite loop.
As such, I have to kill Project thru the task manager.
Is there anyway I can bring up the file without this loop occuring? Thanks.
sub-projects have a considerable number of external links. I have been
making updates to the individual sub-projects. Recently upon opening a
sub-project I received a "circular relationship" error (the successors of a
task refer back to a predecessor of the same task). When I click on the OK
button Project comes up then goes what I can only guess as an infinite loop.
As such, I have to kill Project thru the task manager.
Is there anyway I can bring up the file without this loop occuring? Thanks.