J
Jim Sipe
Running Project Server 2007 SP1.
In a Master Schedule I am getting the "circular reference" message with
cache cleared (nothing in cache). Once the Master Schedule has loaded, it
also loads cache with the remated schedules. If I close and re-open the
Master Schedule with the cache populated I do not get the circular reference
message. I can repeat this and no message. If I then clear cache and open
the Master Schedule, I get the circular reference message. Another Project
Manager gets the same results with the same Master Schedule.
I have validated that all schedules contain no predecessors or successors on
Summary Tasks.
Any ideas?
Jim
In a Master Schedule I am getting the "circular reference" message with
cache cleared (nothing in cache). Once the Master Schedule has loaded, it
also loads cache with the remated schedules. If I close and re-open the
Master Schedule with the cache populated I do not get the circular reference
message. I can repeat this and no message. If I then clear cache and open
the Master Schedule, I get the circular reference message. Another Project
Manager gets the same results with the same Master Schedule.
I have validated that all schedules contain no predecessors or successors on
Summary Tasks.
Any ideas?
Jim