S
Sally
We have a large master plan (about 25 sub plans) and one of the sub plans
died on a circular reference. While we recovered with the help of Microsoft,
a question remains.
The circular reference was created and Server closed the project. The
circular reference was detected when the project was next opened.
Is is correct to assume that Server only checks the labyrinth of linkages
only when opening and not when closing the project?
If so, is there a utility or some fix that can be run before a project is
closed to ensure that this does not happen again. Recovery was not
inconsequential.
died on a circular reference. While we recovered with the help of Microsoft,
a question remains.
The circular reference was created and Server closed the project. The
circular reference was detected when the project was next opened.
Is is correct to assume that Server only checks the labyrinth of linkages
only when opening and not when closing the project?
If so, is there a utility or some fix that can be run before a project is
closed to ensure that this does not happen again. Recovery was not
inconsequential.