S
Samantha Gore
When I open a plan in MSP 2003, it tells me I have a circular reference, but
the task is not showing either predecessors nor successors. I have tried
deleting it and moving it around, and then I get the message again for the
same row number (107).
Also when I try to link other tasks in a group I get a circular link
warning, even though they are new and not linked. If I link them in pairs it
works OK. If I then set the date of the first task, or link it to elsewhere,
none of the dates in the successing tasks adjusts to the correct date.
Am I missing something or is my file corrupted?
Many thanks, Samantha
the task is not showing either predecessors nor successors. I have tried
deleting it and moving it around, and then I get the message again for the
same row number (107).
Also when I try to link other tasks in a group I get a circular link
warning, even though they are new and not linked. If I link them in pairs it
works OK. If I then set the date of the first task, or link it to elsewhere,
none of the dates in the successing tasks adjusts to the correct date.
Am I missing something or is my file corrupted?
Many thanks, Samantha