Circular Relationships

R

RDU

I've inherited yet another bastardized Project file! This time when I open
the file I get a mesage each time informing me that there is a circular
reference problem (sample message below). Each time I resolve a circular
reference, I save the file & close out. Upon re-opening, I'm greeted with yet
another CR problem...it's a never-ending cycle.

All suggestions or ideas appreciated.

--Randy

No calculations can be performed now.
There is a circular reference in task 569 Labeling of <project file name>.
The successors of this task refer back to the task or its predecessors,
causing a circular reference.
To remove the link that is causing the circular reference, select the two
tasks that are causing the circular link, and then click Unlink Tasks on the
Standard Toolbar.
 
J

Jan De Messemaeker

Hi,
Filter for summary tasks, insert the successors column.
Both predecessor and successors column should be empty.
HTH
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top