M
Mickey
Hi Everyone,
I need some clarification regarding what happens once the tracking
method is changed from actual hours to % work complete. I realize
that in-progress tasks will keep actual hours as the tracking method.
However, what happens to a task if it has no actual hours recorded
against it yet, but it was already published in the plan when the
tracking method was still actual hours? I don't view this task as an
in-progress task, but maybe I'm defining in-progress incorrectly.
I have encountered some weird situations where tasks that were never
started before are keeping the ability to enter actual hours against
them even though the plans have been republished using % work
complete. Any ideas why it would be doing this and what I will need
to do in order to correct it?
All thoughts and suggestions are welcome....
Thanks,
Mickey
I need some clarification regarding what happens once the tracking
method is changed from actual hours to % work complete. I realize
that in-progress tasks will keep actual hours as the tracking method.
However, what happens to a task if it has no actual hours recorded
against it yet, but it was already published in the plan when the
tracking method was still actual hours? I don't view this task as an
in-progress task, but maybe I'm defining in-progress incorrectly.
I have encountered some weird situations where tasks that were never
started before are keeping the ability to enter actual hours against
them even though the plans have been republished using % work
complete. Any ideas why it would be doing this and what I will need
to do in order to correct it?
All thoughts and suggestions are welcome....
Thanks,
Mickey