R
Reed
I'm trying to help a local school use Project to schedule library use,
but I can't figure out how to do this with MS Project.
Here's the problem:
1. The library is available in 30-minute slots from 8:00 am until 2:30 pm
Tuesday, Wednesday and Thursday.
2. There are 36 classes that each need to visit the library once during
those three days.
3. Each class must use one of the 30-minute slots.
4. Each class has it's own availability times, with different start and end
times, lunch periods, planning periods and recess periods.
5. I want Project to automatically assign each class to a 30-minute time
slot based on availability of the class.
Can Project do this?
I have assigned the library as a resource that is available Tu-We-Th from
8:00 until 2:30.
I have assigned each class as a resource and set their working times
accordingly (see #4 above).
I can't figure out where to go from here. Am I using the right approach?
Any ideas?
Thanks!
Reed
but I can't figure out how to do this with MS Project.
Here's the problem:
1. The library is available in 30-minute slots from 8:00 am until 2:30 pm
Tuesday, Wednesday and Thursday.
2. There are 36 classes that each need to visit the library once during
those three days.
3. Each class must use one of the 30-minute slots.
4. Each class has it's own availability times, with different start and end
times, lunch periods, planning periods and recess periods.
5. I want Project to automatically assign each class to a 30-minute time
slot based on availability of the class.
Can Project do this?
I have assigned the library as a resource that is available Tu-We-Th from
8:00 until 2:30.
I have assigned each class as a resource and set their working times
accordingly (see #4 above).
I can't figure out where to go from here. Am I using the right approach?
Any ideas?
Thanks!
Reed