Classes of days of week issue

R

Rookie_User

We are creating a monstor of a plan that has multiple departments and ALL
company projects and activities -- we are using the durations only NOT
resourcing at this time. However, I am curious as to how to show some
training activities at the company. For example, if we have 7 classes that
are over a 7 week period and occupy one day a week. I have it setup under
the umbrella task of training, then seven tasks that say training1,2,3,4,etc.
and the duration is one week, BUT it is really only one day, but offered
weekly. How do I show the umbrella as seven week duration but each task has
a one day duration with 4 day "lag"?

Help.. :)
 
J

JulieS

Hi Rookie User,

If the classes occur on the same day of the week (every Monday for
example) you could use a recurring task. Go to Insert > Recurring task.
The duration is one day occurs weekly every week on (select day). Set
the range of recurrance to end after 7.

I hope this helps. Let us know how you get along.

Julie

Visit http://project.mvps.org/ for the FAQs and additional information
about Microsoft Project
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top