We are creating a monstor of a plan that has multiple departments and ALL
company projects and activities -- we are using the durations only NOT
resourcing at this time. However, I am curious as to how to show some
training activities at the company. For example, if we have 7 classes that
are over a 7 week period and occupy one day a week. I have it setup under
the umbrella task of training, then seven tasks that say training1,2,3,4,etc.
and the duration is one week, BUT it is really only one day, but offered
weekly. How do I show the umbrella as seven week duration but each task has
a one day duration with 4 day "lag"?
Help..![Smile :) :)](data:image/gif;base64,R0lGODlhAQABAIAAAAAAAP///yH5BAEAAAAALAAAAAABAAEAAAIBRAA7)
company projects and activities -- we are using the durations only NOT
resourcing at this time. However, I am curious as to how to show some
training activities at the company. For example, if we have 7 classes that
are over a 7 week period and occupy one day a week. I have it setup under
the umbrella task of training, then seven tasks that say training1,2,3,4,etc.
and the duration is one week, BUT it is really only one day, but offered
weekly. How do I show the umbrella as seven week duration but each task has
a one day duration with 4 day "lag"?