P
PM Training12
Has anyone used the PWA option "Clean up Project Server database" to remove
completed tasks in Project Server 2003 SP2a?
On the screen, there is a message that describes deleting completing tasks
and says "...and their associated timephased work and actuals". I found a
Microsoft article that says using this feature will delete the actuals from
the database, but not from the MSP workplan.
We ran a test using the analysis cube (rebuild after deleting completed
tasks) and it appears after using this feature, the work and actuals were
still in the database. Does anyone have first hand experience with this
feature? If it can delete work and actuals from the database -- as the
screen says -- we can't use it because we generate reports from the database.
Thanks.
completed tasks in Project Server 2003 SP2a?
On the screen, there is a message that describes deleting completing tasks
and says "...and their associated timephased work and actuals". I found a
Microsoft article that says using this feature will delete the actuals from
the database, but not from the MSP workplan.
We ran a test using the analysis cube (rebuild after deleting completed
tasks) and it appears after using this feature, the work and actuals were
still in the database. Does anyone have first hand experience with this
feature? If it can delete work and actuals from the database -- as the
screen says -- we can't use it because we generate reports from the database.
Thanks.