J
Jason
Quick background: I manage industrial projects from design, fabrication to
installation. I have been asked by my company to schedule the work flow
through microsoft project 2003.
What is the best way to allocate resources to the fabrication? A typical
scenario would be 6 pieces of equipment going through the shop at one time. I
have the estimated hours for each piece of equipment. We run a shop that at
peak levels has 20 fabricators. Can I simply have one resource called
fabrication at 2000% and adjust the percentage of that resource assigned to
each piece of equipment?
An example would be an item that takes 200hrs to complete. That would
typically have three fabricators working full time (10hr/day) or would be
complete in 7 working days.
Can I have a single fabrication resource? Or do I need 20 seperate
fabricator resources?
Thanks
Jason
installation. I have been asked by my company to schedule the work flow
through microsoft project 2003.
What is the best way to allocate resources to the fabrication? A typical
scenario would be 6 pieces of equipment going through the shop at one time. I
have the estimated hours for each piece of equipment. We run a shop that at
peak levels has 20 fabricators. Can I simply have one resource called
fabrication at 2000% and adjust the percentage of that resource assigned to
each piece of equipment?
An example would be an item that takes 200hrs to complete. That would
typically have three fabricators working full time (10hr/day) or would be
complete in 7 working days.
Can I have a single fabrication resource? Or do I need 20 seperate
fabricator resources?
Thanks
Jason