I am using Project Server 2007 with SharePoint 2007. Recently I applied the
October Cumulative Update to Project Server and shortly thereafter noticed
that whenever I clear the baseline on a project it appears that the baseline
is removed but if I close and reopen the project the baseline shows up again.
This can also be seen in the Project Center where I will clear the baseline
of a project, publish it, refresh the view in Project Center and the original
baseline still displays. If I overwrite the existing baseline with a new one
everything works fine.
I’ve been using Project Server for several years and have never had this
problem up until a few weeks ago. The only thing I can think of that’s
causing it is the October Update that I installed. Is anyone else having
this problem? Do either the December or February updates fix this?
Thanks,
Sam
October Cumulative Update to Project Server and shortly thereafter noticed
that whenever I clear the baseline on a project it appears that the baseline
is removed but if I close and reopen the project the baseline shows up again.
This can also be seen in the Project Center where I will clear the baseline
of a project, publish it, refresh the view in Project Center and the original
baseline still displays. If I overwrite the existing baseline with a new one
everything works fine.
I’ve been using Project Server for several years and have never had this
problem up until a few weeks ago. The only thing I can think of that’s
causing it is the October Update that I installed. Is anyone else having
this problem? Do either the December or February updates fix this?
Thanks,
Sam