ks2008 said:
Dear All,
I am confused with all your answers.
I just wanted to know, what is the meaning of "splitting" here ?
How the MS project handles that on splitting ?
How the MS Project decides the task required to be delayed or required
to be splited ?
"Resource leveling is the process of delaying or splitting "
I do understand, the meaning of delaying. Could you explain splitting
?
Thanks
KS
Suppose you have a two week task you need to schedule. You already have
a task scheduled to start 27 July and last a week. If you don't allow
the first task to split, it can't start until 3 August. That is a
simple delay. If you allow it to split, it could start on 20 July,
continue for a week and then the second half could take place week
beginning 3 August.
Essentially, it is the fragmentation of tasks to mop up smaller amounts
of available resource in your plan.
Note that it does not modify the assignment units and consequently, will
not optimise your plan in this regard.