J
JMJMJM
I'm new to Project and apologize for the basic nature of this question.
However, I've searched several sources for an answer and haven't made
progress.
When I disply the Leveling Gantt view and having cleared leveling, some of
the preleveled tasks do not match the start and end dates that were defined
when I created the task and dependencies. Furthermore, some of the
preleveled tasks show a split which I never entered when defining the task.
Can someone tell me why this is so and how I can get the leveling Gantt view
to display the project without the splits and delays?
Thanks,
JM
However, I've searched several sources for an answer and haven't made
progress.
When I disply the Leveling Gantt view and having cleared leveling, some of
the preleveled tasks do not match the start and end dates that were defined
when I created the task and dependencies. Furthermore, some of the
preleveled tasks show a split which I never entered when defining the task.
Can someone tell me why this is so and how I can get the leveling Gantt view
to display the project without the splits and delays?
Thanks,
JM