M
Michael
I am using Project 2000 to show the links between a set of
technologies and the products being developed that
incorporate them. The best way to describe the situation
is with an example:
Set up tasks for IDs 1, 2, 3 and 4 with the same start and
finish dates. These will represent technologies used to
build products. Then, create a new "product" for task 5,
starting after the finish dates of the technologies and
requiring tasks 1 and 3 as predecessors. Create a
second "product" for task 6, starting after task 5 is
completed (this is important to show what I am talking
about), and requiring tasks 2 and 4 as predecessors.
Then, take a look at the dependency line coming out of
task 3 - if you only look at the picture, this line
intersects with the "products" shown for tasks 5 and 6,
eventhough it is only "really" connected to task 5. This
happens because there is no symbol that appears on the
Project diagram - all that comes out is the connection of
the two lines.
What I am looking for is some kind of "connector" symbol
to be shown for tasks that are truly predecessors - in the
example above, there would be a "dot" at the junction of
tasks 5 and 1, 5 and 3, 6 and 2, 6 and 4. While the
dependency lines would cross between tasks 6 and 3, it
would be clear that these two tasks are not connected
(since there is no "dot" at the junction of the dependency
lines).
I'm sorry about the length of this post, but I was unable
to find a more concise way to describe this problem. Is
there a preference screen (that I haven't found) that
let's me turn this on? Is there a trick that can simulate
this effect? Is this available in a more recent version
of Project?
Thanks for your help.
technologies and the products being developed that
incorporate them. The best way to describe the situation
is with an example:
Set up tasks for IDs 1, 2, 3 and 4 with the same start and
finish dates. These will represent technologies used to
build products. Then, create a new "product" for task 5,
starting after the finish dates of the technologies and
requiring tasks 1 and 3 as predecessors. Create a
second "product" for task 6, starting after task 5 is
completed (this is important to show what I am talking
about), and requiring tasks 2 and 4 as predecessors.
Then, take a look at the dependency line coming out of
task 3 - if you only look at the picture, this line
intersects with the "products" shown for tasks 5 and 6,
eventhough it is only "really" connected to task 5. This
happens because there is no symbol that appears on the
Project diagram - all that comes out is the connection of
the two lines.
What I am looking for is some kind of "connector" symbol
to be shown for tasks that are truly predecessors - in the
example above, there would be a "dot" at the junction of
tasks 5 and 1, 5 and 3, 6 and 2, 6 and 4. While the
dependency lines would cross between tasks 6 and 3, it
would be clear that these two tasks are not connected
(since there is no "dot" at the junction of the dependency
lines).
I'm sorry about the length of this post, but I was unable
to find a more concise way to describe this problem. Is
there a preference screen (that I haven't found) that
let's me turn this on? Is there a trick that can simulate
this effect? Is this available in a more recent version
of Project?
Thanks for your help.