P
Project Server Slave
Hello,
I've got a test instance of Project Server 2007 almost all the way
configured. When its done being setup, I need to transfer the
contents to a Production instance and a Development instance. Can I
just backup the databases and restore them with a different name, then
create a new PWA site and point to the databases? Will this cause any
issues? We've not created any Workspace sites, just created custom
fields, populated the resource pool, created security groups, etc.
Can you give me a best practice for doing this sort of thing? I need
all three instances to run on the same box, without any problems.
Thanks!
I've got a test instance of Project Server 2007 almost all the way
configured. When its done being setup, I need to transfer the
contents to a Production instance and a Development instance. Can I
just backup the databases and restore them with a different name, then
create a new PWA site and point to the databases? Will this cause any
issues? We've not created any Workspace sites, just created custom
fields, populated the resource pool, created security groups, etc.
Can you give me a best practice for doing this sort of thing? I need
all three instances to run on the same box, without any problems.
Thanks!