T
Thomas Bräutigam
Hi,
is there a possibility to close tasks to update for periods also? For
example to close My Tasks Updates for September?
Or do we have to use timesheets instead?
But then we would have the problem that the project manager is not
involved in the approval process....but only the timesheet manager...
Regards
Thomas
PS: Question belongs to Project Server 2007 of course
is there a possibility to close tasks to update for periods also? For
example to close My Tasks Updates for September?
Or do we have to use timesheets instead?
But then we would have the problem that the project manager is not
involved in the approval process....but only the timesheet manager...
Regards
Thomas
PS: Question belongs to Project Server 2007 of course