Close Task Where No Was Work Performed

D

Darrell

I have project managers who want to retain tasks in their schedules where no
work was performed so that it is documented that the work was considered but
eventually not necessary and so that the original baseline remains intact. I
have found that some may be removing the resource and then zeroing the work
and not the duration. These tasks eventually become corrupted and the finish
dates jump way out. Is this a division by zero issues in the D=W/U
calculation since the task has a duration but work and resource are zero? Has
anyone else seen this issue?

Darrell
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top