Mocha
If we want to hide or remove those completed or inactive tasks from the list
in the "Select Task" dialog box, we can visit PWA -> Server Settings ->
"Close Tasks to Update" under the "Time and Task Management" -> select the
specific project and those tasks you want to hide/remove from the list,
click on Submit button -> repeat the above to select those tasks again and
ensure they are still checked, click on Publish button.
After the above steps, those tasks will not be displayed in the list on the
"Select Task" dialog box.
my questions are :
1. I have done lock the task and the top task level, but in next period
timesheet, those task (top level) will be display in the list on the "Select
Task" dialog box. Is it right?
I add line to the task (top level) and fill the actual in timesheet. what's
the function of task (top level), th task(top level) should not be displayed
in the list on the "Select Task" because we had locked it
2. the PM must select one by one the project file which have percent
completed 100%, is there the way to hide/remove the completed task from list
without submit and publish case one by one project file?
thx a lot for your helping
in the "Select Task" dialog box, we can visit PWA -> Server Settings ->
"Close Tasks to Update" under the "Time and Task Management" -> select the
specific project and those tasks you want to hide/remove from the list,
click on Submit button -> repeat the above to select those tasks again and
ensure they are still checked, click on Publish button.
After the above steps, those tasks will not be displayed in the list on the
"Select Task" dialog box.
my questions are :
1. I have done lock the task and the top task level, but in next period
timesheet, those task (top level) will be display in the list on the "Select
Task" dialog box. Is it right?
I add line to the task (top level) and fill the actual in timesheet. what's
the function of task (top level), th task(top level) should not be displayed
in the list on the "Select Task" because we had locked it
2. the PM must select one by one the project file which have percent
completed 100%, is there the way to hide/remove the completed task from list
without submit and publish case one by one project file?