We’ve been asked by the development team to create weekly tasks for some
items for DB resources. If there is nothing required of that resource for
that given week, it is my understanding that if they enter zero hours against
the task, this will still not close it out. Is there something that the
resource should be doing, so that it does close out this task? The AMs have
been having to change the percent completion to 100% and it is just causing
some extra work for them.