B
bgriffwork
We've been told by consultants that the best way to close out tasks is:
1. Have the resource set Remaining Work to 0 in PWA.
2. In Project select Tools > Tracking > Update Tasks, and set Remaining
Duration to zero.
This seems to work, but very often afterthe plan is republished, saved,
closed, and re-opened, the % Compllete field will be less than 100%. We
cannot seem to figure out the pattern. Sometimes our steps work, sometimes
they don't.
By the way, our standard is Fixed Duration/non-Effort driven. Any help
would be appreciated.
1. Have the resource set Remaining Work to 0 in PWA.
2. In Project select Tools > Tracking > Update Tasks, and set Remaining
Duration to zero.
This seems to work, but very often afterthe plan is republished, saved,
closed, and re-opened, the % Compllete field will be less than 100%. We
cannot seem to figure out the pattern. Sometimes our steps work, sometimes
they don't.
By the way, our standard is Fixed Duration/non-Effort driven. Any help
would be appreciated.