Closing Tasks to updates

P

PhilB

We are currently using MS Project Server 2007 and like to use the close tasks
to updates option. Is there anyway to do this from Project Professional
instead of PWA? If not, that would be a great thing to have.
 
R

Ray McCoppin

Set the Task Flag field called "Published" to NO, and the assignments will
not longer appear to the resources as being avalialbe for statusing.

Hope this helps
--
Ray McCoppin

http://www.randsmanagement.com
SRS gantt charts
Project Server 2007 Archival Tool
 

Ask a Question