Collaboration-Publishing

J

Jeff Lofgren

I am in the process of implementing and testing MS Project
2002 Enterprise Server. I am setup with security as an
Administrator and Project Manager. I have established an
enterprise resource pool and a project on the enterprise
server. Most everything is working fine, with the
exception of Publishing. I assigned myself to 3 tasks on
my work plan and published new and changes to myself. The
e-mail notifies me that I have some changes, but when I go
to my Home Page or Task Page is says that I am not
assigned to any tasks. If I go to the Resources Page it
shows the tasks that I have published. I have checked the
permissions and they seem to b set up correctly.

Any ideas on what I have not set up correctly that would
give me a message that says I have published my changes
when I publish from my work plan, but does not actually
publish them to my Home Page or Task Page?

Jeff
 
D

David McDermott

Jeff

I had a similar problem a while ago. Bizarrely it is now
fixed although I am not sure how. All I do know is that I
was doing something with the portfolio modeler, allowed it
to change resource assignments and this then republished
them and now resources have tasks.

Not sure why I originally published it the tasks did not
show. This may not be of much help to you but may shed
some light on it, maybe try republishing.

Anyway at least you aren't alone in this.
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top