Hello Melissa,
As there are no formulas in MS Project 98, you can't do set this as an
automatic feature without a VBA procedure.
If you are not found of VBA, you can use a simple way (not automatic) :
- Activate the Using Resource... filter for a resource
- Select all tasks
- Format / Bar...
- Select a color for that resource...
- Activate the Using Resource... filter for an other resource ...
Hope this helps,
Gérard Ducouret