Hello Jake,
See FAQ 31 "Customizing Task Bars" at:
http://project.mvps.org/faqs.htm
Although the title of the FAQ says Project 2000, it still applies.
If you have more than one resource assigned, you'll want to use a
slightly different formula. If you wanted to color tasks assigned
to the resource named "Fred", but Fred was not the only resource
assigned, the formula would be:
IIf(Instr([Resource Names],"Fred")>0,Yes,No)
I hope this helps. Let us know how you get along.
Julie
Project MVP
Visit
http://project.mvps.org/ for the FAQs and additional
information about Microsoft Project