Is there a way to combine multiple Projects so that they intertwine their dates without being dependent on one another? I need to be able to see what is happening per week for all the projects without linking the projects. I am using Project 2000, and would appreciate any help!
 
G

Gérard Ducouret

Hello Jonathan,
Create a brand new project which could be named "Consolidation.mpp"
Then : Insert / Project...
The Task Usage view will display everything you want week per week.

Hope this helps,

Gérard Ducouret

Jonathan said:
Is there a way to combine multiple Projects so that they intertwine their
dates without being dependent on one another? I need to be able to see what
is happening per week for all the projects without linking the projects. I
am using Project 2000, and would appreciate any help!
 