Combining Project And Moving Tasks

R

Raja

Hi,
Is it possible to Combine two diffrent projects into a single project and
also move a particular task from one project to another project. when merging
the project or moving the task the actual work done by the resources must
also be moved.

is this possible ????
 
G

Gérard Ducouret

Raja,
Yes, you can combine several projets (max number : 1000) :
Insert / Project...
But you can't drag & drop a task from one projet to another one. You'll have
to copy/paste the task. May be several copy/paste to keep all the task
information. Not very safe.

Hope this helps,

Gérard Ducouret
 
R

Raja

But does the actual work hours entered by the resource in the time sheet
remain ?
--
Regards
Raja Annamalai


Gérard Ducouret said:
Raja,
Yes, you can combine several projets (max number : 1000) :
Insert / Project...
But you can't drag & drop a task from one projet to another one. You'll have
to copy/paste the task. May be several copy/paste to keep all the task
information. Not very safe.

Hope this helps,

Gérard Ducouret
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top