Combining tasks

A

Ashley Silver

Assuming one of two tasks are no longer necessary (but stored as part of the
baseline), how does one combine the tasks easily so that the final task has
the combined dependencies, and (for a bonus prize) the baseline somehow
reflects the combined task?

I have a pilot group of tasks and a "the rest/full" group of tasks - we are
no cancelling the pilot project and combining the tasks.
 