Communicating with Project

M

Mike

Is there a way to have access, at pre-determined
intervals, transmit data from its fields into MS Project?

I"m 99.9 percent sure I know the answer is "NO", but I
want to be 100 percent sure and you guys are the best.

Thanks,

Mike
 
B

Bryan Martin

Set up a visual basic script to run in the task scheduler which creates an
access application and executes whatever code you need it to.

Bryan Martin
 