I need to compare the exceptions listed in several plans against a base
template. I would like to try doing this by exporting the underlying tables
into MS Access. Which table and fields do I need to home in on to list the
working day exceptions?
 
J

JulieS

Hi Steve,

I don't have Project 2007 handy right now but you can discover what
fields/tables you can use to get exceptions through the Project 2007
SDK.

http://msdn.microsoft.com/en-us/library/ms510779.aspx

You can save the data from the reporting database through Report >
Visual Reports, Save data, Save database.

I hope this helps. Let us know how you get along.

Julie
Project MVP

Visit http://project.mvps.org/ for the FAQs and additional
information about Microsoft Project
 