M
Mike Jones
I'm confused.
I'd like to specify a number of tasks, give them each an amount of work,
then assign them to a resource. I'm expecting that leveling should
move the start and end dates of the tasks so that the resource
consistently has their assigned % of work. The tasks should follow one
another--one should be completed before the next one starts.
Instead, I'm seeing the tasks start in parallel. Project tweaks the
assign resources percentages to reflect that. So I go in and change the
% back to whats expected.
Rather than level the tasks, the resource is grossly overallocated, with
the tasks still in parallel.
What needs to happen here? I could put in dependencies, but I don't
think that's necessarily the best way to solve the problem. I want
Project to do the scheduling for me!
Thanks.
I'd like to specify a number of tasks, give them each an amount of work,
then assign them to a resource. I'm expecting that leveling should
move the start and end dates of the tasks so that the resource
consistently has their assigned % of work. The tasks should follow one
another--one should be completed before the next one starts.
Instead, I'm seeing the tasks start in parallel. Project tweaks the
assign resources percentages to reflect that. So I go in and change the
% back to whats expected.
Rather than level the tasks, the resource is grossly overallocated, with
the tasks still in parallel.
What needs to happen here? I could put in dependencies, but I don't
think that's necessarily the best way to solve the problem. I want
Project to do the scheduling for me!
Thanks.