S
San
I have created project with a phase having about 100 sub-tasks. I tried to
track the actual start and actual finish of each task. However, it's only 2
tasks with 100% complete, the % complete of the phase was 23%. I noticed that
the % complete did change if different actual finish date was input. In
particularly, this actual finish date was much longer than the baseline
finish date. Before this task was completed, % of complete was only 1%
Was this "% complete" indicate the correct % complete of the overall project ?
Or should I use "% work complete" instead ? Can you explan more on the "%
work complete" ? thanks.
track the actual start and actual finish of each task. However, it's only 2
tasks with 100% complete, the % complete of the phase was 23%. I noticed that
the % complete did change if different actual finish date was input. In
particularly, this actual finish date was much longer than the baseline
finish date. Before this task was completed, % of complete was only 1%
Was this "% complete" indicate the correct % complete of the overall project ?
Or should I use "% work complete" instead ? Can you explan more on the "%
work complete" ? thanks.