% complete and graph representation

T

TKeire

Hello again......

I have a standard calendar and 3 resource calendars

Resource A: 6d working week.
Resource B: 5d working week.
Resource C: 7d working week.

I have set up 3 identical tasks for all 3 resources, starting 26/04/06 with
dur 24d.

I now update the tasks to reflect 4d completed and 20d remaining....17%
complete, which comes up correct in the table for each task.

On the Gannt chart, Resource A reflects what 4d work entails and the
%complete bar has progressed to complete through 01/05..as expected

Resource B has decided to progress itself to complete through to 06/05. In
my opinion it should have moved to 02/05 as Saturday was a non working day so
the 4th day was Monday

Resource C has decided to progress itself to complete through 27/04, I think
it should have moved to 30/04 as Sunday was a working day for this Resource.

Can someone explain what is going on here as I am bewildered.

Also on another note, I have another task with Resource B which is scheduled
for 24d but when I hold the mouse over the bar on the Gannt chart it tells me
calendar days for duration.....ie. 29d......this does not happen for any
other task for Resource B???

Thanks in advance

Tony
 