J
Jesse
I have an MS Project 2003 schedule. The tasks are setup Fixed Duration. I'm
using the Work field to estimate and capture level-of-effort time spent on
the task. I'm using the start/duration/finish to estimate and capture
calendar time for each task.
When the task is complete (% work complete) and all the Work is entered --
the task may not show completed (with the check mark) in the Indicator field
because it appears that is driven from the duration and % complete.
What is a best practice (process and/or steps) for when a task is 100% work
complete to also set it to 100% complete?
using the Work field to estimate and capture level-of-effort time spent on
the task. I'm using the start/duration/finish to estimate and capture
calendar time for each task.
When the task is complete (% work complete) and all the Work is entered --
the task may not show completed (with the check mark) in the Indicator field
because it appears that is driven from the duration and % complete.
What is a best practice (process and/or steps) for when a task is 100% work
complete to also set it to 100% complete?