% Complete and % Work Complete

H

Haris

Hi,

I've got my Time Sheets setting with Managed Periods and I've added 3 fields
to the TS view: Remaining Work, % Complete and % Work Complete. The Remaining
Work field appears as editable to the resources but the other two don't. What
am i doing wrong here? I remember I'd these % fields as editable when
initially I'd installed PWA.
Looking forward.

Regards,
Haris
 
D

Dale Howard [MVP]

Haris --

To use Managed Time Periods, Project Server requires that you use the "Hours
of work done per day or per week" method of tracking. When you use this
method of tracking, team members enter their Actual Work on a daily or
weekly basis in the timesheet grid on the right side of the View my tasks
page, and can adjust the Remaining Work value in the table on the left side
of the page. This method of tracking does not allow team members to adjust
the % Work Complete value for their tasks. Hope this helps.
 
H

Haris

Dale:

Thanks a lot :). I was suspicious about it being this way, just needed to
make sure I'm thinkin on the right track. Thanks again!

Regards,
Haris
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top