H
Haris
Hi,
I've got my Time Sheets setting with Managed Periods and I've added 3 fields
to the TS view: Remaining Work, % Complete and % Work Complete. The Remaining
Work field appears as editable to the resources but the other two don't. What
am i doing wrong here? I remember I'd these % fields as editable when
initially I'd installed PWA.
Looking forward.
Regards,
Haris
I've got my Time Sheets setting with Managed Periods and I've added 3 fields
to the TS view: Remaining Work, % Complete and % Work Complete. The Remaining
Work field appears as editable to the resources but the other two don't. What
am i doing wrong here? I remember I'd these % fields as editable when
initially I'd installed PWA.
Looking forward.
Regards,
Haris