% Complete is based on duration. For example, if you have a 10 day task, and
you are completed through the 5th day, the % complete is 50%. But % Work
Complete is based on effort. For example, if you have 100 hours of work to
complete a task, and you are 20 hours into the task, you are only 20% Work
Complete. These two can differ for a given task. For example, let’s say it
takes 40 hours to paint a room which will take a week (assuming 8 hours a
day). Say I worked only 10 hours after the first 2 days. I am 40% Complete
(only 3 more days left), but I am only 25% Work Complete. I need to make up
the additional 30 hours in the next three days if I plan to finish it on
schedule.