% Complete Data Analysis View

L

L8rdays

Hello....

Is there any way to pull % Complete in a data analysis view?

I'm trying to create a chart that shows the # of projects by their %
complete. Didn't want to do custom reporting, just was hoping for something
quick.

Thanks!
 
D

Dale Howard [MVP]

L8rdays --

No, there is no default way to add the % Complete field to a Data Analysis.
That would require exending the OLAP cube. Hope this helps.
 
J

Jonathan Sofer [MVP]

Couldn't you add a custom calculated field in your OLAP cube that divides
Actual Work/Work or are you looking for duration based % Complete?

Jonathan
 