A
Andrew
I run a macro to get the planned % complete for bars so that I can compare
planned against actual. This works fine except for summary bars. The %
complete planned, works out the Planned % along the bar, ie 5 weeks out of 10
weeks = 50%. The actual % by MSP does not seem to match the planned %. How
does MSP work out the actual % of a summary bar, if the Planned % matches the
actual % of individual bars why is there a discrepancy ?
Andrew
planned against actual. This works fine except for summary bars. The %
complete planned, works out the Planned % along the bar, ie 5 weeks out of 10
weeks = 50%. The actual % by MSP does not seem to match the planned %. How
does MSP work out the actual % of a summary bar, if the Planned % matches the
actual % of individual bars why is there a discrepancy ?
Andrew