M
Merry
Hello,
I encounter an issue. All tasks have been updated in MS Project 2007 with
Complete % = 100%, but when I inquiry in EPM PWA, one task Complete % is 99%,
which results in the whole project Complete % is 99%.
PS: When I open the project by MS Project 2007, it reminds me "an inactive
reource has remaining task....".
What is the reason.
Thanks
Zhang
I encounter an issue. All tasks have been updated in MS Project 2007 with
Complete % = 100%, but when I inquiry in EPM PWA, one task Complete % is 99%,
which results in the whole project Complete % is 99%.
PS: When I open the project by MS Project 2007, it reminds me "an inactive
reource has remaining task....".
What is the reason.
Thanks
Zhang