% Complete in "Projects" view at PWA

  • Thread starter Alexander Barvinsky
  • Start date
A

Alexander Barvinsky

Hi,
I entered actual values in Project Professional and publish all information.
% Complete is 53, when I view project plan in Pro. When I use view "Projects"
in PWA it's show me 0. Where I'm wrong?


Alerxander Barvinsky
pm4pm.org
 
G

Gary L. Chefetz [MVP]

If you do this to an assignment that was previously published, you need to
republish the assignment selecting to overwrite actual work if you want this
to show up in PWA.
 
A

Alexander Barvinsky

Seems it doesn't work. I'm opening plan, republishing all assignments, but
at PWA in %Complete I see 0.
Any ideas?
If you do this to an assignment that was previously published, you need to
republish the assignment selecting to overwrite actual work if you want this
to show up in PWA.

Alerxander Barvinsky
pm4pm.org
 
G

Gary L. Chefetz [MVP]

State the exact steps you're taking, be specific with the menu choices.
 
A

Alexander Barvinsky

State the exact steps you're taking, be specific with the menu choices.
1. Open MS Project Pro
2. Open Project Plan
3. Callaborate -> Publish -> Republish all assigments
Alerxander Barvinsky
pm4pm.org
 