Hi,
I entered actual values in Project Professional and publish all information.
% Complete is 53, when I view project plan in Pro. When I use view "Projects"
in PWA it's show me 0. Where I'm wrong?
Alerxander Barvinsky
pm4pm.org
I entered actual values in Project Professional and publish all information.
% Complete is 53, when I view project plan in Pro. When I use view "Projects"
in PWA it's show me 0. Where I'm wrong?