Dale
I have noticed that on occassion where a resource completes a task in less
hours than planned, the task will show as 100% complete on that resources
task sheet but will not show as 100% on the actual project plan. For example
a task estimated to take 8 hours of work over a three day period. The
resource actually completes the work in 4 hours and records that time and
changes their remaining work to 0 resulting in that task showing 100% on
their task view, yet when the update is processed by the Project Manager, the
actual project plan shows only 50% complete.
hours than planned, the task will show as 100% complete on that resources
task sheet but will not show as 100% on the actual project plan. For example
a task estimated to take 8 hours of work over a three day period. The
resource actually completes the work in 4 hours and records that time and
changes their remaining work to 0 resulting in that task showing 100% on
their task view, yet when the update is processed by the Project Manager, the
actual project plan shows only 50% complete.