M
Macedo
Hello.
Recently I performed a migration to EPM-2007.
When the migrated projects are published, the resources receive
messages for changed tasks, however, some tasks are wrong, as examples
of three different cases:
a. Work: 30h Remaining Work: 27,3h % Complete: NaN
b. Work: 3,2h Remaining Work: 0h % Complete: NaN
c. Work: 8h Remaining Work: 0h % Complete: 100
Tasks "b" and "c" were completed in 03/june/09.
Is there a way to recalculate the Project information and send only
the correct tasks in the e-mail?
Thanks.
Recently I performed a migration to EPM-2007.
When the migrated projects are published, the resources receive
messages for changed tasks, however, some tasks are wrong, as examples
of three different cases:
a. Work: 30h Remaining Work: 27,3h % Complete: NaN
b. Work: 3,2h Remaining Work: 0h % Complete: NaN
c. Work: 8h Remaining Work: 0h % Complete: 100
Tasks "b" and "c" were completed in 03/june/09.
Is there a way to recalculate the Project information and send only
the correct tasks in the e-mail?
Thanks.