J
Jason Leung
I created a project with only one task and saved it as XML. I used the Word
editor to open the XML file and updated both %Complete and % Work Complete to
50% and then saved the XML. I used Project Professional 2002 to import the
XML file and discovered the %Work Complete has been updated successfully to
50% but the %Complete remains at 0%. Is there any reasons why %Complete would
not pick up the XML update?
editor to open the XML file and updated both %Complete and % Work Complete to
50% and then saved the XML. I used Project Professional 2002 to import the
XML file and discovered the %Work Complete has been updated successfully to
50% but the %Complete remains at 0%. Is there any reasons why %Complete would
not pick up the XML update?