Hi guys, i'm running a complex project where tasks are tending to be
done out of order (as most coding tasks tend to) so instead of doing
tasks in order a-b-c they're doing 50% of a then 50% of e then 75% of
c then finishing off a - and so on.
what i'm keen for the mpp to do is take the completed section of the
task on the gantt chart and put that before the progress line
(currently set to display the current date) and leave the remaining
chunk of work where it should be in the gantt chart - thus more
accurately reflecting the end date as it's removing work already done
from the end-date calculation.
At the moment, it's keeping the entire task bar there in the gantt
chart even though 80% of a task might be complete - and calculating
the start and finish dates as though the task hasn't even been
started.
thanks!
done out of order (as most coding tasks tend to) so instead of doing
tasks in order a-b-c they're doing 50% of a then 50% of e then 75% of
c then finishing off a - and so on.
what i'm keen for the mpp to do is take the completed section of the
task on the gantt chart and put that before the progress line
(currently set to display the current date) and leave the remaining
chunk of work where it should be in the gantt chart - thus more
accurately reflecting the end date as it's removing work already done
from the end-date calculation.
At the moment, it's keeping the entire task bar there in the gantt
chart even though 80% of a task might be complete - and calculating
the start and finish dates as though the task hasn't even been
started.
thanks!