M
MBA40118
When I look at summary progress on a summary bar, compared with the %
complete for the Summary, the Summary Progress bar does not "Appear" to be
mapping out the correct amount on the Summary Bar. Example, if the Percent
complete is 33%, the summary progress bar will show 25%, or 40% on the bar
chart. This is not the case for all, but only some. I am using Project 2007.
Is this a matter of how it prints, or is it calculating something other than
percent complete to get skewed on the bar chart??
complete for the Summary, the Summary Progress bar does not "Appear" to be
mapping out the correct amount on the Summary Bar. Example, if the Percent
complete is 33%, the summary progress bar will show 25%, or 40% on the bar
chart. This is not the case for all, but only some. I am using Project 2007.
Is this a matter of how it prints, or is it calculating something other than
percent complete to get skewed on the bar chart??