If the % complete is updated in Project Professional and then saved/republished, the Project View is updated and accurate in PWA, but the Task View is not the same.

EggHeadCafe.com - .NET Developer Portal of Choice
http://www.eggheadcafe.com
 
D

Dale Howard [MVP]

Brent --

You must republish the assignments using Collaborate - Publish - Republish
Assignments, select the "Overwrite actual work entered by resources" option,
and then click OK. Hope this helps.
 