S
sgm
I have a project with fixed duration, non-effort driven
tasks. We are using the % complete column (not % work
complete) to reflect teams' progress on tasks in
increments of 25%. The problem is that Project tends to
recalculate intermittantly, and override the % complete
entries. This happens most directly when the Status Date
is updated.
One workaround we found was to use the Physical %
Complete column instead, since entries were not getting
overriden. However, the Physical % Complete does not
appear to roll up to summary tasks. We are using Project
2003.
Any ideas on why Project is recalcing or how to get
Physical % Complete to roll up to summary tasks?
Thanks!!!
tasks. We are using the % complete column (not % work
complete) to reflect teams' progress on tasks in
increments of 25%. The problem is that Project tends to
recalculate intermittantly, and override the % complete
entries. This happens most directly when the Status Date
is updated.
One workaround we found was to use the Physical %
Complete column instead, since entries were not getting
overriden. However, the Physical % Complete does not
appear to roll up to summary tasks. We are using Project
2003.
Any ideas on why Project is recalcing or how to get
Physical % Complete to roll up to summary tasks?
Thanks!!!