We have Project Server 2007 SP1 installed and are currently using it a lot
for some small projects which are being entered in as Activities. The tasks
are assigned to resources, who then complete their timesheets, sync with
their task lists, which then show 100% completed task, the creator of the
activity then approves the Task Update, but the % Complete and % Work
Complete still show as 0% in the Project Centre.
Anyone now what we are missing?