S
Sally
Hello,
What is general perspective of using the Physical % Complete versus the %
Complete field?
My company uses the % Complete field for our earned value reporting. If the
task is 50% complete, we mark it as 50%, 75% complete...we type in 75%.
Another company, our customer, has instructed us to use the Physical %
Complete field. They want us to use the "Update Project" feature and update
all the tasks through the status date (currently our period end). Then they
are going to use whatever MSProject calculates the % Complete to be for their
reporting metrics.
Has anyone ever used this method to calculate their % Complete? If
so....what value added metrics does this process generate?
We are using MSProject 2007 on a 25,000 line item schedule and we do NOT
resource load it. We use another tool for resources.
Thanks!
Sally
What is general perspective of using the Physical % Complete versus the %
Complete field?
My company uses the % Complete field for our earned value reporting. If the
task is 50% complete, we mark it as 50%, 75% complete...we type in 75%.
Another company, our customer, has instructed us to use the Physical %
Complete field. They want us to use the "Update Project" feature and update
all the tasks through the status date (currently our period end). Then they
are going to use whatever MSProject calculates the % Complete to be for their
reporting metrics.
Has anyone ever used this method to calculate their % Complete? If
so....what value added metrics does this process generate?
We are using MSProject 2007 on a 25,000 line item schedule and we do NOT
resource load it. We use another tool for resources.
Thanks!
Sally