J
Jerry
Hi
I am a little confused here and will be thanful for guidance.
We wanted to use % Work Complete to track project progress and uncheck
the calculation option update task status updates resource status from
Options -> Calculations. When team members sent update and PM accept
that Work complete is update and %Complete is not. Thats Right.
1. Tell me one thing when i set a task %Complete to 100% it
automatically set 100% to %work Complete. Why
2. What if PM decide after setting task to 100% that some more work is
required and PM set the remaining work to some value. The %complete
and %Work Complet both changed to 99%. Why
But if the task has summary it shows some other value why...
Correct me if i am wrong
a. if i set %complete to 100% Project will set my Actual Work and %Work
Complet to 100% Right. (yes/No)
b. if i set %work complete to 100% (or set remainig work to 0) it will
not effect %Complete. (yes/no)
I will be thankful if some one explains it here.
Thanks and Regards
Jerry
I am a little confused here and will be thanful for guidance.
We wanted to use % Work Complete to track project progress and uncheck
the calculation option update task status updates resource status from
Options -> Calculations. When team members sent update and PM accept
that Work complete is update and %Complete is not. Thats Right.
1. Tell me one thing when i set a task %Complete to 100% it
automatically set 100% to %work Complete. Why
2. What if PM decide after setting task to 100% that some more work is
required and PM set the remaining work to some value. The %complete
and %Work Complet both changed to 99%. Why
But if the task has summary it shows some other value why...
Correct me if i am wrong
a. if i set %complete to 100% Project will set my Actual Work and %Work
Complet to 100% Right. (yes/No)
b. if i set %work complete to 100% (or set remainig work to 0) it will
not effect %Complete. (yes/no)
I will be thankful if some one explains it here.
Thanks and Regards
Jerry