B
Bnh1310
Can anyone tell me why the % Complete no. in PWA view does not seem to match
the project tracking line in the gantt chart in Project Center. For example
I have a number of projects ranging from 10 - 90% complete using the %
complete outline code. When viewing that in PWA with the Gantt chart on the
right side. They do not seem to match. Not even close. I've even added the %
work complete to the same view to see if it matches. I've tested it with
various degree's of completion. For example: Identical project starts dates
and times but different amounts of work. Niether seem to match. % complete
will show 80%. Tracking line appears at 50 % complete. What does the
tracking line indicate? Others 20% complete tracking line is at 50%.
the project tracking line in the gantt chart in Project Center. For example
I have a number of projects ranging from 10 - 90% complete using the %
complete outline code. When viewing that in PWA with the Gantt chart on the
right side. They do not seem to match. Not even close. I've even added the %
work complete to the same view to see if it matches. I've tested it with
various degree's of completion. For example: Identical project starts dates
and times but different amounts of work. Niether seem to match. % complete
will show 80%. Tracking line appears at 50 % complete. What does the
tracking line indicate? Others 20% complete tracking line is at 50%.